Certification Process_Jacob Star

Certification Process

SNI Certification Procedure

SNICertification Procedure

 

企业微信截图_17424585331960 

1. Fill in the SNI Application Form

fill inSNIApplication Form

The application form constitutes one of the mandatory requirements for the SNI documentation, and it must be completed bilingually in both Chinese and English. To obtain the SNI certification application form, please reach out to SINOQUAL for procurement.

The application form isSNIThis is an integral part of the document submission and must be filled in both Chinese and English.SNICertification application form, please contactSINOQUALContact to claim.

2. Submit the applicant's legal and technical documents

Applicants are required to submit their company's legal and technical documents. Please see the details for details.appendix1.

3. Verify & GAP Assessmentverifyand gap assessment

SINOQUAL conducts verification and gap assessments on the documents submitted by applicants for SNI certification to determine whether they meet the conditions for a site audit.

SINOQUALrightSubmitted by the applicantSNIVerification and gap assessment of certification documents to determine if the applicant meets the requirements for on-site audits

3. Producer Quality Management System AuditProducer quality management system audit

Checking the conformity between the completeness and adequacy of the producer’s quality management system document against the application requirements. If any discrepancies are found, they will be asked to correct them within two months.

The producer's quality management system documentation will be checked for completeness and adequacy in accordance with applicable requirements. If any discrepancies are found, they will be required to correct them within two months.

4. Sample Testsampletest

Sample testing by taking a sample of the product to be tested and labeling the test sample (LCU), then sealing. Sample testing is carried out in an accredited test laboratory.

By taking a sample of the product to be tested andLCU) are labeled and then sealed for sample testing. Sample testing is carried out in an accredited testing laboratory.

5. Sample AssessmentSample evaluation

After the testing process, a Test Result Certification will be issued. If the results do not meet the standards, they will be asked to repeat until they are in accordance with the provisions. If it cannot meet the standards, the application will be rejected.

After the testing process is completed, a certificate of test results will be issued. If the results do not meet the standards, they will be asked to repeat until they meet the regulations. If the standards are not met, the application will be rejected.

6. Certification DecisionCertification decision

An independent team will meet to discuss the results of the audit and testing.

An independent panel will meet to discuss the findings of the audit and testing.

7. Submission of SPPT-SNIsubmitSPPT-SNI

After the group meeting, the review team will identify the relevant companies or producers. They will be categorised based on legality and integrity, standard terms, production processes, and quality management systems.

After the group meeting,Judging TeamThe relevant companies or producers will be identified and classified according to legal integrity, standard terms, production process and quality management system.

 

 

8. Issue SNI certificates GrantSNICertificate

 

 

 

 

appendix1

Document requirementsDocuments Requirement

Applicant's legal documentsLdoesn't matterDocuments

As we know, in doing SNI, there should be one LocalRrepresentative mentioned on the certificate. The role of this LR is as the one who will be responsible of the product in Indonesia. So, in case there is something happen in the future, authority knows who to contact.

 

Local representative here can be the distributor, importer, local brand representative, or any other party. And during the process, local representative is mandatory to submit SNI document requirements, including legal documents. Common documents that need to be submitted are:

· Copy of Company Notary DeedCompany notarization deed(Articles of Association of Akta Pendirian Perserian Entities)Instances

· Photocopy of business registration number (SIUP, TDP, and NIB)Copy of business registration (SIUP, TDP and NIB)

· Copy of Tax Payer ID (NPWP)Copy of taxpayer ID (NPWP)

· Trademark Registration Letter from the Director General of Intellectual Property Rights / Trademark Certificate (Sertifikat Pendaftaran Merk from DITJEN HKI)Trademark registration letter/trademark certificate from the Director of the Intellectual Property Office (Sertifikat Pendaftaran Merk from DITJEN HKI)

· Brand Transfer Certificate or cooperation letter between brand owner and Local Representative (Only if applicant/Local Representative is not brand owner)Brand Transfer Certificate or Letter of Cooperation between the brand owner and the local representative (only if the applicant/local representative is not the brand owner)

· Company Organization Chart approved by the Chairpersontop managementApproved company organizational chart

· Importer Identification Number (API) (if applicant/local representative is not manufacturer)Importer Identification Number (API) (if applicant/local representative is not the manufacturer)

· Copy of Quality Management System Certificate or other management certificateCopies of quality management system certificates or other management certificates

 

TECHNICAL DOCUMENTS

· Factory legal documents; translated to Indonesian languageFactory Legal DocumentsBusiness License; Translate into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Industrial permit; translated to Indonesian languageIndustrial license; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Factory Organizational Chart ; translated to Indonesian languageFactory Organization Chart; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Factory Company ProfileFactory Company Profile

· Company LayoutCompany layoutpicture

· Circuit DiagramCircuit DiagramIf any)

· A copy of valid Certificate of Management System ISO 9001 or equivalent “Documents of ISO 9001:2015A copy of a valid management system certificate ISO 9001 or equivalent “ISO 9001:2015 Document”

· Copy of Quality Manual ; translated to Indonesian languageCopy of the Quality Manual; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Copy of Master List Document; translated to Indonesian languagehostdocumentCopy of the manifest document; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Copy of QC/QA Flow Chart; translated to Indonesian languageQC/QA Copy of flowchart; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Copy of Organization Chart and Job Description; translated to Indonesian languageCopies of organizational chart and job descriptions; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Copy of Risk Analysis; translated to Indonesian languageA copy of the risk analysis; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Artwork/design of SNI marking on the product and packaging; translated to Indonesian languageIllustration/design of the SNI mark on products and packaging; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Product specification for each modelProduct specifications for each model

· Photos of product, including wiring diagram pictureProduct photos, including wiring diagram images

· Instruction Manual (User Manual) in Indonesia language; translated to Indonesian languageInstruction manual (user manual) in Indonesian; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· Installation Manual in Indonesia language; translated to Indonesian languageInstallation manual in Indonesian; translated into IndonesianDocument translation is handled by the SINOQUAL Indonesia team)

· CB Report (if any)CB report (if any)

· BOM List BOM

· List of Production equipment of the factory (draft attached)Factory Production Equipment List (Draft Attached)

· List of Testing equipment of the factory (draft attached)Factory Testing Equipment List (Draft Attached)

· List of main component and its detail information with formal like table below: A list of main components and their detailed information is formally shown in the following table:

NoSerial number

Component/MaterialComponents/Materials

Manufacturer/TrademarkManufacturer/Trademark

Type / ModelType

Technical Data

Standard Applied

Mark(s) of Conformity

1







2













Regarding the requirements for SNI files, the content has been thoroughly outlined above. However, please note that the aforementioned list is not set in stone. As policies continue to evolve and product characteristics vary, you may need to provide additional supporting documents to meet the SNI certification requirements. Therefore, when preparing for certification, it is essential to stay closely informed about the latest developments in relevant policies and to thoroughly assess the characteristics of your products to ensure that the documents provided are complete, accurate, and compliant with SNI certification standards.The SNI documentation requirements are detailed above. However, please note that this list is not set in stone. As policies evolve and product features vary, you may need to provide additional supporting documentation to meet SNI certification requirements. Therefore, when preparing for certification, please closely monitor the latest policy developments and thoroughly evaluate your product's features to ensure that the documentation you provide is complete, accurate, and meets SNI certification standards.

 

 

Latest News

In today's interconnected world, the Halal market is not just a niche market, but a major global...